ATCO Pipelines – Pembina-Keephills Transmission Line (PKTL)

http://www.rbsomerville.com/files/2020/03/Blue-Rapids-HDD.jpg
Owner:
Job Number: 19008
Role: Pipeline
Engineer:
Primary Work Type: Pipeline
Other Work Type: Horizontal Directional Drilling
Status: Complete
Location: Alberta
Duration:: Aug-2019 – Mar-2020
Value: 50M +
Contract Type: Lump Sum

Construction of the Pembina-Keephills Transmission Project comprised of approximately 58.6km of NPS 30 pipe, 800m of NPS 24 pipe, and 200m of NPS 20 pipe.
Construction included eleven (11) Horizontal Directional Drills for a total of 6,024m and installation of 4 Valve Assemblies (including one pig launcher and receiver).