Duration:: Jun-2016 – Oct-2016
Value:
Contract Type:

The installation of 815m of NPS 20 was successfully completed using our American Augers DD440T HDD. The pilot was completed using a 12″ duckbill style jetting assembly utilizing a Paratrack 2 wireline guidance system to steer the bit to the exit point while maintaining a 20m depth of cover to facilitate running line restrictions from overhead hydro towers and a narrow ROW corridor.  Pilot was completed ahead of schedule and right on target.   Working with a mud engineer and skilled mud tech we were able to complete the 30″ reaming of the bore hole and successfully pull in the 815m of 20″steel pipe with a lower than anticipated pull pressure.