Trans Mountain North Thompson 6 Pipe Replacement

http://www.rbsomerville.com/files/2020/11/IMG_0997.jpg
Job Number: 19006
Role:
Engineer:
Primary Work Type: Pipeline Construction
Other Work Type: Horizontal Directional Drilling
Status: Completed
Location: British Columbia
Duration:: Jul-2019 – Dec-2019
Value:
Contract Type: Time & Material

Somerville installed 800m of new 24″ replacement pipeline under the North Thompson River in Blue River, BC.  Post tie-ins, the existing piping through the river was grouted (approximately 565m of 24″) and decommissioned.