Somerville has remained in business for over sixty years by consistently executing projects. We have helped to build many strong communities across this country, one project at a time, and in fact due to our collective and respective efforts have helped to build a strong country. We understand mega-projects these days require a distinct level of expertise and experience, which we have, but we are quite flexible – and friendly – too.

Our crews are admired for their professionalism, and their personal high regard for safety and the environment, whether completing projects both large and small. While on this page you will always see an updated selection of our most recent projects. Dig deeper. Within our specifically constructed project vault, we hope you’ll enjoy perusing our impeccable history, especially when viewed across a truly immense spectrum of activity.

Line 9 Re-route (Don River)

http://www.rbsomerville.com/files/2017/04/DSC00165.jpg

Client: Enbridge Pipelines Location: Ontario Status: Duration: Sep-2013 to Feb-2014

The primary work involved rerouting a section of Enbridge Pipelines Line 9, from approximately KP 3081.35 to KP 3082.07 in Toronto, Ontario.   This section of Line 9 is a 30 inch (762 mm) OD pipeline …  Visit project ›

Ottawa Reinforcement

http://www.rbsomerville.com/files/2017/03/Airport-4.jpg

Client: Enbridge Gas Distribution Location: Status: Duration: Aug-2013 to Nov-2013

Robert B. Somerville was contracted to complete 3 directional drills as part of a new NPS 24 pipeline being constructed in Ottawa. Somerville utilized the DD185 to complete a 300 meter crossing under …  Visit project ›

Red Deer – AltaLink 138 kV 80L Underground Transmission

http://www.rbsomerville.com/files/2016/08/PA050226-1.jpg

Client: EHV Power Location: Alberta Status: Duration: Jan-2015 to Nov-2015

The AltaLink 138kV 80L underground transmission project formed an important part of 18 separate developments designed to strengthen the electrical grid in the greater Red Deer, Alberta area. The ductb …  Visit project ›

EPCOR – Arena Project

http://www.rbsomerville.com/files/2016/08/14214-Picture.jpg

Client: EPCOR DISTRIBUTION & TRANSMISSION INC. Location: Alberta Status: Duration: Sep-2014 to Feb-2015

With the construction of the new “ICE District” in downtown Edmonton which will consist of the Rogers Place and many other new buildings and developments, Somerville was contracted by EPCOR to constru …  Visit project ›

NORTH EAST CALGARY CONNECT PROJECT (NECC)

http://www.rbsomerville.com/files/2016/08/FullSizeRender-1.jpg

Client: ATCO Pipelines Location: Alberta Status: Duration: Jul-2015 to Feb-2016

This project included the installation of 16.7 km of 24” (610mm) pipeline including 4 valve stations in North East Calgary. This Urban Pipeline Replacement Project in 2015 was part 1 of 3 segments to …  Visit project ›

Mirabel Quebec Class Upgrade

http://www.rbsomerville.com/files/2016/02/image12.jpeg

Client: TransCanada Location: Quebec Status: Completed Duration: Aug-2015 to Nov-2015

This project required the replacement of 1075m of 24″ pipeline in an urban area. This presented challenges in that the pipeline needed to remain operational throughout the entire replacement. Stopple …  Visit project ›

Regent Park Revitalization – Phase III – Site Servicing

http://www.rbsomerville.com/files/2016/02/IMG_20151113_091117.jpg

Client: Daniels Corporation Location: Ontario Status: Completed Duration: Jun-2015 to Dec-2016

Somerville completed Phase II of the Regent Park Revitalization project.  In June 2015, Phase III began and Somerville was contracted to undertake the construction of the site servicing including: Mun …  Visit project ›

Payne to Sarnia Pipeline

http://www.rbsomerville.com/files/2016/02/DSC04893.jpg

Client: Union Gas Location: Ontario Status: Completed Duration: May-2015 to Aug-2015

Somerville was contracted to construct approximately 4.8km of NPS 20 pipeline from Union Gas’s Payne Compressor Station to the Sarnia Industrial Line, Novacor Station and a new pressure control and me …  Visit project ›

Mainline Valve 402 Installation

http://www.rbsomerville.com/files/2016/01/photo-13.jpg

Client: TransCanada Location: Manitoba Status: Completed Duration: Sep-2015 to Oct-2015

This project required the installation of a 30″ mainline valve on an existing pipeline. The scope included the installation of piles to support the valve, powergas piping and valve actuators for the v …  Visit project ›

Maintenance Hydrotest NPS 18 Ferrier

http://www.rbsomerville.com/files/2016/01/IMG_14521.png

Client: TransCanada Location: Alberta Status: Completed Duration: Jun-2015 to Sep-2015

Somerville performed  hydro testing services on the TCPL NPS 18 Ferrier Lateral just outside Rocky Mountain House.  The project consisted of 4 centre cuts and  5 maintenance test sections.  A tether i …  Visit project ›