For this project, Somerville used a DD185 drill to drill under Trafalgar Rd and the 16 Mile Creek to replace a 495m section of NPS12. The bore was drilled through limestock rock using a 6 3/4" mud motor and wireline guided steering to pilot successfully. The hole was reamed out to 18" to allow the NPS12 pipeline to be installed. Project was completed on time.
Pipeline
Trafalgar Rd NPS 12 HDD
Project Information
Client: NPL Canada
Job Number: 23009-07
Work Type: Integrity & Maintenance
Location: Milton, Ontario
Owner: Sun Canadian-Pipe Line Company
Role: Subcontractor
Status: Complete
Duration: 2023-07-04T04:00:00.0000000Z2023-07-31T04:00:00.0000000Z