This project involved the installation of 700m of NPS 16 ST pipe to be installed under a bridge and creek via Horizontal Directional Drill for Enbridge Gas Distribution. This project is phase III of the reinforcement project that Enbridge has been constructing since 2006.
Horizontal Directional Drilling
Scarborough Reinforcement - Phase III - 9th Line HDD
Project Information
Client: Aecon Utilities
Job Number: 10022
Work Type: Heavy Rigs (100k & larger)
Location: Ontario
Contract Type: LSC
Owner: Enbridge Gas Distribution
Role: Subcontractor
Status: Completed