This project was part of the overall Pearson Airport Expansion Project. PCL Aecon Joint Venture was the overall Construction Manager. Robert B. Somerville was subcontracted to Black & McDonald to complete the underground services and pipelines. The project included the installation of 600m of dual 10" insulated Perma Pipe as Hot & Cold Water Pipelines to Heat the new Terminal Buildings at Person International Airport. Also includes the construction of 4 Snow Melt Pits, and installation of 8" PE Natural Gas Pipeline. The hot and chilled water in the pipelines is generated at the Central Utilties Plant (CUP) located off of Elmbank Road
Pipeline
Apron Stage 1 Area 4 - Apron Utilites
Project Information
Client: Black & McDonald Limited
Job Number: 04021
Work Type: Distribution Pipeline
Location: Ontario
Contract Type: LSC
Owner: Greater Toronto Airports Authority
Role: Subcontractor
Status: Completed