Project is to replace existing steel mains and services in the McLeod area of Edmonton. Area is primarily residential and some commercial buildings and townhouses. Project involves installation of 7,885m of PE mains up to 6" and 607 services, with approximately 57 addresses requiring pressure upgrades. New mains and services will primarily be installed by directional drilling. Also involved with the replacement of service lines is to move any existing inside gas meter to the outside of the building. Inside gas meter work will consist of primarily residential houses with 200 series meters, and some larger commercial rotary meters.