Scope of work included installation of 8.7 km of 30 pipeline including 3 valve stations in East Calgary. This Urban Pipeline Replacement Project in 2015 was part 2 of 3 segments to replace aging infrastructure that currently runs within the City of Calgary. Execution of the work included 9 HDD sections totalling 4280m and 4420m of open cut.


Pipeline
East Calgary Connect Project (ECC)
Project Information
Client: ATCO Pipelines
Job Number: 15026
Work Type: Mainlnie Pipeline
Location: Alberta
Contract Type: Unit Price
Role: General Contractor
Status: Completed