Somerville was contracted to decommission and replace an existing NPS 8 with NPS 12 pipeline. The work was completed in three phases and included 580m of horizontal directional drilling of NPS12 steel pipe under Highway 406. The new NPS 12 line serves as a critical connection between two of the major pipeline networks in Ottawa.