This project required the replacement of 1075m of 24" pipeline in an urban area. This presented challenges in that the pipeline needed to remain operational throughout the entire replacement. Stopple fittings and 24" bypasses were installed to ensure gas flow during construction activities.
Pipeline
Mirabel Quebec Class Upgrade
Project Information
Client: TransCanada
Job Number: 15025
Work Type: Integrity & Maintenance
Location: Quebec
Contract Type: Cost Plus
Owner: TransCanada Pipelines
Role: General Contractor
Status: Completed