The North Cental Corridor project required the replacement of the Wabasca River Crossing which included ~700m NPS36 HDD. Winter work was a necessity based on muskeg and poor ground conditions in warmer months. This high use line could not be completed with an outage. Instead stopple bypass was utilized for final tie-ins.