Installation of 16.7 km of 24 (610mm) pipeline including 4 valve stations in North East Calgary. This Urban Pipeline Replacement Project in 2015 was part 1 of 3 segments to replace aging infrastructure that currently runs within the City of Calgary. Execution of the work included 12 direction drill segments totalling 4855m and 11,901m of open cut.
Pipeline
NORTH EAST CALGARY CONNECT PROJECT (NECC)
Project Information
Client: ATCO Pipelines
Job Number: 15021
Work Type: Mainlnie Pipeline
Location: Alberta
Contract Type: Unit Price
Owner: ATCO Pipelines