This project required the placement of new underground plant on the existing roadway boulevards in front of the homes, up to the existing meter bases, to facilitate the removal of the current backlot electrical system. All trenches were open cut, and were direct buried ducts only, with the exception of road crossings that were concrete encased. Cable installation, energization, and changeovers were done by North Bay Hydro.
Infrastructure
Pinewood Backlot Elimination, Phase 5-12
Project Information
Client: North Bay Hydro
Job Number: 10839
Work Type: Distribution Powerlines
Location: Ontario
Contract Type: UPC
Owner: North Bay Hydro
Role: General Contractor
Status: Completed