Pipeline

ADT Pipeline Connector Project

Project Information

Client: Keyera Corporation
Job Number: 14006
Work Type: Integrity & Maintenance
Location: Alberta
Owner: Keyera Corporation
Role: General Contractor
Status: Completed
Somerville was contracted by Keyera Corporation to install approximately 2.5km of NPS12 & 2.5km of NPS8 pipeline. The project was installed primarily using HDD technology due to the restricted space and limited ROW availability. This required numerous drills to be bundled making for difficult tie-ins. This project also included facility construction at the ADT facility and tie-in locations. A new requirement for AC mitigation was implemented successfully for the construction installation. AC Mitigation is a new safety regulation required by pipeline owners in Alberta.