The project involved the replacement of the existing sanitary pumping sump with a new 2.4m x 2.4m precast reinforced concrete pumping sump chamber including all internal piping and appurtenances. The work also included relocating two existing submersible pumps to the new chamber, the installation of approximately 96 metres of 50mm dia. HDPE pipe from new chamber to existing sanitary manhole on roadway using horizontal directional drilling. The project was located at the Rouge River Community Centre.
Infrastructure
Rouge River CC - Sanitary Sump Pump Replacement
Project Information
Client: Town of Markham
Job Number: 10009
Work Type: Water & Sewer
Location: Ontario
Contract Type: LSC
Owner: Town of Markham
Role: General Contractor
Status: Completed