Installation of approximately 20.8km of NPS 20 and 2km of NPS 12 in the South West Edmonton Transportation Utility Corridor (TUC). The pipelinewas installed within a 10m ROW with 20m adjacent work space. There were numerous HDD crossings including the North Saskatchewan River, White Mud Creek and the Anthony Henday at multiple locations.