Pipeline

Steel Mains Replacement (SMR) - King Edward Park 2

Project Information

Client: ATCO Gas
Job Number: 14503
Work Type: Distribution Pipeline
Location: Alberta
Contract Type: Unit Price
Owner: ATCO Gas
Role: Prime Contractor
Status: Completed
Download PDF
Project is to replace existing steel mains and services in the King Edward Park area of Edmonton. Area is primarily residential and some commercial buildings. Project involves installation of 1,380m of PE mains up to 2", 700m of PE mains between 3" and 4", and 265 services. New mains and services will primarily be installed by directional drilling. Also involved with the replacement of service lines is to move any existing inside gas meter to the outside of the building. Inside gas meter work will consist of primarily residential houses with 200 series meters, and commercial meters up to 2M rotary meters.