The project is to replace existing steel mains and services in the town of Spruce Grove, just West of Edmonton. The area is primarily residential with some commercial buildings. This project involves the installation of 2,800m of PE mains up to 2", 1,800m of PE mains between 3" and 4", and 354 services. New mains and services will primarily be installed by directional drilling. Also involved with the replacement of service lines is to move any existing inside gas meter to the outside of the building. Inside gas meter work will consist of primarily residential houses with typically 200 series meters, and commercial meters up to 2M rotary meters.
Pipeline
Steel Mains Replacement (SMR) - Millgrove
Project Information
Client: ATCO Gas
Job Number: 15503
Work Type: Distribution Pipeline
Location: Alberta
Contract Type: Unit Price
Owner: ATCO Gas
Role: Prime Contractor
Status: Completed