Project scope includes the hydrostatic testing three sections of NPS42 totaling approximately 44.4km. This project includes the pre-test isolation and re-instatement of sales taps along with excavation, welding and coating. Project water source was 5.5km away from the fill point requiring pumping water over 5.5km and installation of 3 C-Rings.
Pipeline
TC Energy - NPS42 Edson CAS50 Hydrotest
Project Information
Client: TC Energy
Job Number: 19010
Work Type: Integrity & Maintenance
Location: Alberta
Contract Type: Cost Plus
Owner: TC Energy
Role: Pipeline
Status: Complete