1395.0 trench metres - 4 x 100 mm ducts placed by Directional Drill, In Ground Horizontal Jack and Bore 450 mm steel casing under CN Main line for 52.0 metres, 320 trench metres of trench excavation over existing buried cables, Tie ins to existing manholes.
Infrastructure
Underground Service Upgrade, Fibre to the Node Project -Trafalgar Rd., Oakville
Project Information
Client: Bell Canada
Job Number: 09057
Work Type: Communications and Fibre Optics
Location: Ontario
Contract Type: UPC
Owner: Bell Canada
Role: General Contractor
Status: Completed
Duration: 2009-02-01T05:00:00.0000000Z2009-06-01T04:00:00.0000000Z