Project is to replace existing steel mains and services along 118 Avenue from 142 St to 149 St in Edmonton. Area is primarily commercial. Project involved installation of 850m of PE mains ranging from 2" to 4", and 55 services. Also involved with the replacement of service lines was to move any existing inside gas meter to the outside of the building. Inside gas meter work consisted of meter work from 200 series meters up to 2M rotary meters.