Pipeline

Whitby Class Upgrade

Project Information

Client: TC Energy
Job Number: 22383
Work Type: Integrity & Maintenance
Location: Ontario
Contract Type: Cost Plus
Owner: TC Energy
Role: Prime Contractor
Status: Complete
Duration: 2022-05-01T04:00:00.0000000Z2022-10-30T04:00:00.0000000Z

This class replacement is driven by the pipeline’s proximity to a new proposed residential subdivision in the vicinity of the pipeline ROW. The project involved the replacement of 1201m of NPS20 and 1196m of NPS24. This included pipe replacement through 230m of environmentally sensitive forest. The existing lines were isolated, removed, the new pipe welded, installed and tested prior to commissioning, all within tight execution timelines.